The industrial redeployment of the St-Feuillien Brewery

The St-Feuillien Brewery is investing in the construction of its new Brewery and the acquisition of a brand new bottling line.

The first groundbreaking ceremony took place on December 6, 2021. The new buildings were quickly built and the structure was closed in July 2022.

Back in pictures

february 2022 - earthworks february 2022 - earthworks
march 2022 - earthworks march 2022 - earthworks
end of March 2022 - installation of walls end of March 2022 - installation of walls
july 2022 -structural work closed july 2022 -structural work closed
  • The work continues on its way: a 50-meter underground pipeline that leads beer from the brewhouse directly to the bottling line.
  • Unloading of the gas boiler.
  • Arrival and installation of our brand new bottling line.
  • Installation of the CIP (Cleaning In Place) equipment in the future brewhouse.
  • end of July 2022 - pipeline end of July 2022 - pipeline
    august 2022 - boiler arrival august 2022 - boiler arrival
    september 2022 - installation of the bottling line september 2022 - installation of the bottling line
    october 2022 - CIP october 2022 - CIP

    Beginning of December: start-up of our bottling line.

    1st test - St-Feuillien blonde 1st test - St-Feuillien blonde
    boxing boxing
    bottling line bottling line

    The buildings are ready to receive the equipment. The moving of the brewhouse installations will be done in two steps.

    • Octobre 2022 : October 2022: removal of the guard tanks.
    • Janvier 2023 : January 2023: relocation of the brewhouse and fermentation tanks.

    The Antenne Centre team and Ann Friart report on the event.

    october 2022 - relocation of maturation tank october 2022 - relocation of maturation tank
    january 2023 - relocation of silo january 2023 - relocation of silo
    january 2023 - relocation of fermentation tank 750 HL january 2023 - relocation of fermentation tank 750 HL
    relocation january 2023 relocation january 2023

    The mechanical and electrical installation of the brewing equipment was completed.
    The installation was tested and production resumed at the end of February 2023.